Utan Kayu River Retaining Wall Repair to be Completed Early December

The repair of Utan Kayu River retaining wall in Matraman, East Jakarta run by third party since November 3 is targeted to complete in early December.

The broken part is along 45 meter

East Jakarta Water Resource Sub-agency's Maintenance Section Head, Puryanto Palebangan, explained the 88-meter long retaining wall, which is still under repair by a third party, was broken due to being eroded by the overflow of the Utan Kayu River during heavy rain.

Anwar: Repair of Utan Kayu River Sheet Pile must Be Accelerated

"The broken part is along 45 meter," he said, Tuesday (11/12).

Project Implementer, Harlen Sitorus, said the repair is now entering the finishing stage.

"Personnel are working on sloop casting and plastering of the retaining wall. It is targeted to complete in early December.

Linked News
Popular News indeks
  1. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye974 personAldi Geri Lumban Tobing
  2. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye934 personAldi Geri Lumban Tobing
  3. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye834 personFakhrizal Fakhri
  4. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye710 personAldi Geri Lumban Tobing
  5. Chinese New Year Holiday, Ancol Flocked by Visitors

    access_time16-02-2026 remove_red_eye608 personAnita Karyati